Progress Update
Oct. 18, 2026: The Design drawings are expected to be complete by December 2026. The Brothers in White Chapel (BIW) Board and Architect will soon begin the process of selection of a Construction Manager at Risk (CMAR). The CMAR will aid in developing the construction drawings and feasible ways to reduce and control costs. The CMAR will guarantee the price quote for construction not to exceed. However, prior to beginning of construction, all required funds must be available. As of today, approximately $250,000 is needed for completion of the Pack Unit. Next Board meeting will be Oct. 26th. Fund-raising activities continue with an expected completion of the build out of the Pack chapel by end of 2027 assuming that we have all funds needed by 2026.